15A NCAC 07H .1504      GENERAL CONDITIONS

(a)  Permittees shall allow representatives of the Department of Environmental Quality to make inspections at any time to ensure that the activity being performed under authority of the General Permit set forth in this Section is in accordance with the terms and conditions prescribed herein.

(b)  The permit set forth in this Section shall not be applicable to proposed construction where the Department has determined based on an initial review of the application that notice and review pursuant to G.S. 113A-119 is required because there are unresolved questions concerning the proposed activity's impact on Areas of Environmental Concern.

(c)  No new basins shall be allowed that result in closure of shellfish waters according to the closure policy of the Division of Marine Fisheries, 15A NCAC 18A .0911.

 

History Note:        Authority G.S. 113A‑107(a),(b); G.S. 113A-108; 113A‑113(b); 113A‑118.1; 113-229(c1);

Eff. July 1, 1984;

Amended Eff. May 1, 1990; December 1, 1987;

RRC Objection due to ambiguity Eff. May 19, 1994;

Amended Eff. July 1, 2015; August 1, 1998; July 1, 1994;

Readopted Eff. October 1, 2022.